GSLC · Question #238
During which of the following processes, probability and impact matrix is prepared?
The correct answer is D. Perform Qualitative Risk Analysis. The probability and impact matrix is a key tool and technique used during the Perform Qualitative Risk Analysis process to prioritize individual project risks.
Question
During which of the following processes, probability and impact matrix is prepared?
Options
- APerform Quantitative Risk Analysis
- BPlan Risk Responses
- CMonitoring and Control Risks
- DPerform Qualitative Risk Analysis
How the community answered
(41 responses)- A2% (1)
- B7% (3)
- C2% (1)
- D88% (36)
Why each option
The probability and impact matrix is a key tool and technique used during the Perform Qualitative Risk Analysis process to prioritize individual project risks.
Perform Quantitative Risk Analysis uses numerical methods such as Monte Carlo simulation and decision tree analysis to assign numerical probability values, not a probability and impact matrix.
Plan Risk Responses focuses on developing options, strategies, and actions to address prioritized risks - it consumes the output of qualitative analysis rather than producing the matrix.
Monitor and Control Risks involves tracking identified risks, implementing response plans, and evaluating risk process effectiveness; it does not produce the probability and impact matrix.
Perform Qualitative Risk Analysis uses the probability and impact matrix to assess and prioritize risks by multiplying or combining their likelihood of occurrence with the magnitude of their effect on project objectives, enabling the team to focus attention on high-priority risks.
Concept tested: Probability and impact matrix in qualitative risk analysis