Question

You and your project team have identified the project risks and now are analyzing the probability and impact of the risks. What type of analysis of the risks provides a quick and high-level review of each identified risk event?

Options

  • AQuantitative risk analysis
  • BSeven risk responses
  • CQualitative risk analysis
  • DA risk probability-impact matrix