A playbook contains five tasks in total. An administrator runs the playbook and four out of five tasks finish successfully, but one task fails. What will be the status of the playbook after it is run?

The correct answer is C. Failed. Playbook jobs that include one or more failed tasks are labeled as Failed in Playbook Monitor. A failed status, however, does not mean that all tasks failed. Some individual actions may have completed successfully.

Alerting and Incident Response

Question

A playbook contains five tasks in total. An administrator runs the playbook and four out of five tasks finish successfully, but one task fails. What will be the status of the playbook after it is run?

Options

  • AAttention required
  • BUpstream_failed
  • CFailed
  • DSuccess

How the community answered

(46 responses)
  • B
    4% (2)
  • C
    93% (43)
  • D
    2% (1)

Explanation

Playbook jobs that include one or more failed tasks are labeled as Failed in Playbook Monitor. A failed status, however, does not mean that all tasks failed. Some individual actions may have completed successfully.