A technician has established a plan of action. Which of the following should the technician do next?

The correct answer is D. Implement a solution.. After a technician has established a plan of action, the next step in the troubleshooting process is to implement the solution. This involves executing the plan that was carefully crafted to resolve the issue. Following this, the technician would then verify system functionality

IT Concepts and Terminology

Question

A technician has established a plan of action. Which of the following should the technician do next?

Options

  • AVerify system functionality.
  • BIdentify preventive measures.
  • CDocument the findings.
  • DImplement a solution.

How the community answered

(45 responses)
  • A
    2% (1)
  • C
    4% (2)
  • D
    93% (42)

Explanation

After a technician has established a plan of action, the next step in the troubleshooting process is to implement the solution. This involves executing the plan that was carefully crafted to resolve the issue. Following this, the technician would then verify system functionality and take preventive measures if necessary, but implementation comes immediately after planning.