A business case for a project claims that the new system will provide managers with more time to think creatively about strategic issues. What would this be classified as in a cost-benefit analysis?

The correct answer is C. An intangible benefit. See the full explanation below for the reasoning.

Question

A business case for a project claims that the new system will provide managers with more time to think creatively about strategic issues. What would this be classified as in a cost-benefit analysis?

Options

  • AAn intangible cost.
  • BA tangible benefit.
  • CAn intangible benefit.
  • DA tangible cost.

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    7% (2)
  • C
    79% (22)
  • D
    11% (3)