BCS-ISEB
FBA15 · Question #79
A business case for a project claims that the new system will provide managers with more time to think creatively about strategic issues. What would this be classified as in a cost-benefit analysis?
The correct answer is C. An intangible benefit. See the full explanation below for the reasoning.
Question
A business case for a project claims that the new system will provide managers with more time to think creatively about strategic issues. What would this be classified as in a cost-benefit analysis?
Options
- AAn intangible cost.
- BA tangible benefit.
- CAn intangible benefit.
- DA tangible cost.
How the community answered
(28 responses)- A4% (1)
- B7% (2)
- C79% (22)
- D11% (3)
Community Discussion
No community discussion yet for this question.