Question

What is the role of a Stakeholder Map in a Green IT programme?

Options

  • AIt provides performance measurement of key stakeholders.
  • BIt highlights the responsibilities of each stakeholder.
  • CIt identifies where the roles of stakeholders overlap.
  • DIt identifies where stakeholders will influence the programme.