What is bottom-up scheduling?

The correct answer is A. Team members representing each role generate time estimates and schedules for. See the full explanation below for the reasoning.

Question

What is bottom-up scheduling?

Options

  • ATeam members representing each role generate time estimates and schedules for
  • BThe program manager estimates the time required for each team member to complete his or
  • CThe program manager builds a master project schedule based on industry standards for each
  • DThe solution manager estimates the time required for each team member to complete his or

How the community answered

(20 responses)
  • A
    70% (14)
  • B
    15% (3)
  • C
    10% (2)
  • D
    5% (1)