Which of the following is obtained from the Identify step of the Risk Management Process?

The correct answer is A. The downstream effect of the risk. See the full explanation below for the reasoning.

Question

Which of the following is obtained from the Identify step of the Risk Management Process?

Options

  • AThe downstream effect of the risk
  • BThe priority of the risk
  • CThe probability of the risk
  • DThe mitigation of the risk

How the community answered

(31 responses)
  • A
    81% (25)
  • B
    3% (1)
  • C
    10% (3)
  • D
    6% (2)