nerdexam
EXIN

EX0-101 · Question #124

Which of the following availability management activities is/are considered to be proactive as opposed to reactive? 1. Monitoring system availability 2. Designing availability into a proposed solution

The correct answer is D. 2 only. See the full explanation below for the reasoning.

Question

Which of the following availability management activities is/are considered to be proactive as opposed to reactive? 1. Monitoring system availability 2. Designing availability into a proposed solution

Options

  • ANone of the above
  • BBoth of the above
  • C1 only
  • D2 only

How the community answered

(35 responses)
  • A
    14% (5)
  • B
    6% (2)
  • C
    3% (1)
  • D
    77% (27)

Community Discussion

No community discussion yet for this question.

Full EX0-101 Practice