Question

How does Agile bring predictability to the Planning process?

Options

  • ABy allowing the customers to review the progress often.
  • BBy assigning most of the responsibility to the Product Owner.
  • CBy making the team self-organized and self-planning.
  • DBy providing early visibility into the team's progress.