EX0-008 · Question #37

Agile planning happens at multiple levels including a daily plan, an sprint plan and a strategic plan. What term best describes the multi-level planning?

The correct answer is A. Planning Onion. Planning Onion (A) is the correct term because it describes the layered, hierarchical nature of Agile planning - from strategic goals at the outer layers down to daily tasks at the center, resembling the concentric rings of an onion. Each layer represents a different planning…

Agile Way of Thinking

Question

Agile planning happens at multiple levels including a daily plan, an sprint plan and a strategic plan. What term best describes the multi-level planning?

Options

  • APlanning Onion
  • BPlanning Poker
  • CSprint Planning

How the community answered

(31 responses)
  • A
    90% (28)
  • B
    3% (1)
  • C
    6% (2)

Explanation

Planning Onion (A) is the correct term because it describes the layered, hierarchical nature of Agile planning - from strategic goals at the outer layers down to daily tasks at the center, resembling the concentric rings of an onion. Each layer represents a different planning horizon (portfolio, product roadmap, release, sprint, daily), and they nest inside one another.

Planning Poker (B) is a technique, not a framework - it's a consensus-based estimation game where team members use numbered cards to estimate effort, having nothing to do with multi-level planning structure.

Sprint Planning (C) is just one single level of the planning hierarchy (the sprint layer), so it cannot describe the multi-level concept as a whole.

Memory tip: Picture an actual onion - each layer you peel back is a shorter time horizon. Big outer layer = long-term strategy; tiny inner core = today's standup. If the question mentions "levels" or "layers" of planning, think onion.

Topics

#agile planning#planning onion#multi-level planning#planning hierarchy