What is the expected outcome of the first Sprint on a project?
The correct answer is A. A few working, tested features from the Product Backlog. Scrum defines a Sprint as a time-boxed iteration that must deliver a potentially shippable product increment - meaning real, working, tested functionality pulled from the Product Backlog. That's why A is correct: the whole point of Sprint 1 is to produce something tangible and…
Question
What is the expected outcome of the first Sprint on a project?
Options
- AA few working, tested features from the Product Backlog
- BArchitecture and high-level design of the Product
- CAssignment of the team, Product Owner and Scrum Master
- DA well-defined release plan for the Product
How the community answered
(17 responses)- A88% (15)
- B6% (1)
- C6% (1)
Explanation
Scrum defines a Sprint as a time-boxed iteration that must deliver a potentially shippable product increment - meaning real, working, tested functionality pulled from the Product Backlog. That's why A is correct: the whole point of Sprint 1 is to produce something tangible and functional, not just plans or paperwork.
- B is wrong because Scrum explicitly rejects up-front architecture phases ("Big Design Up Front"). Design emerges iteratively across Sprints.
- C is wrong because team formation and role assignment happen before Sprint 1 begins, during project setup - not as an outcome of the Sprint itself.
- D is wrong because a "release plan" is a traditional waterfall artifact. Scrum uses a Product Backlog and Sprint Goals instead; long-range release planning is not a Sprint deliverable.
Memory tip: Think of each Sprint as a mini-product delivery - if you can't demo working software at the end, you didn't complete the Sprint. The word "increment" is key: Scrum Sprints always increment (add to) a working product.