Which area of management within programme quality tracks and protects project outputs?

The correct answer is B. Asset. See the full explanation below for the reasoning.

Question

Which area of management within programme quality tracks and protects project outputs?

Options

  • AProcess
  • BAsset
  • CInformation
  • DSupply chain

How the community answered

(18 responses)
  • A
    17% (3)
  • B
    72% (13)
  • C
    6% (1)
  • D
    6% (1)