Which does NOT describe a programme?

The correct answer is D. Blueprint focus is on changing the entire organization. See the full explanation below for the reasoning.

Question

Which does NOT describe a programme?

Options

  • ARisk focus is on collective project risks
  • BQuality focus is on a range of management processes
  • CBenefit focus is on the rigour of profiling and realization
  • DBlueprint focus is on changing the entire organization

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    15% (4)
  • C
    4% (1)
  • D
    78% (21)