nerdexam
EXIN

EX0-003 · Question #94

Which is a part of programme planning?

The correct answer is B. Involving widespread discussions to include ambiguities and unknowns. See the full explanation below for the reasoning.

Question

Which is a part of programme planning?

Options

  • AEnsuring the programme manages its projects in detail
  • BInvolving widespread discussions to include ambiguities and unknowns
  • CChecking the sustainability of the programme against the Business Case
  • DProviding progress information for benefits reviews

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    83% (25)
  • C
    10% (3)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full EX0-003 Practice