Which of the following is NOT a principle of programme risk management?

The correct answer is B. Capture all project risks centrally. See the full explanation below for the reasoning.

Question

Which of the following is NOT a principle of programme risk management?

Options

  • AUnderstand the programme context Risk change
  • BCapture all project risks centrally
  • CInvolve stakeholders
  • DMonitor for early warning indicators

How the community answered

(21 responses)
  • A
    14% (3)
  • B
    71% (15)
  • C
    5% (1)
  • D
    10% (2)