EX0-003 · Question #65
Which of the following is NOT a principle of programme risk management?
The correct answer is B. Capture all project risks centrally. See the full explanation below for the reasoning.
Question
Which of the following is NOT a principle of programme risk management?
Options
- AUnderstand the programme context Risk change
- BCapture all project risks centrally
- CInvolve stakeholders
- DMonitor for early warning indicators
How the community answered
(21 responses)- A14% (3)
- B71% (15)
- C5% (1)
- D10% (2)