nerdexam
EXIN

EX0-003 · Question #52

Why may a Business Change Manager be included within a project board structure of one of the programme's projects?

The correct answer is B. Provide a specific focus on transition and operational stability. See the full explanation below for the reasoning.

Question

Why may a Business Change Manager be included within a project board structure of one of the programme's projects?

Options

  • AMonitor the project's finances against the costs of the programme
  • BProvide a specific focus on transition and operational stability
  • CProvide the procedures to manage project risks
  • DSupply the project team with an understanding of the complete programme

How the community answered

(51 responses)
  • A
    4% (2)
  • B
    75% (38)
  • C
    8% (4)
  • D
    14% (7)

Community Discussion

No community discussion yet for this question.

Full EX0-003 Practice