Question
Which is NOT a reason for the process Realizing the Benefits?
Options
- AEnsure that project direction is closely linked with programme objectives
- BEnsure that project outputs are suitable for operational use
- CInform the Senior Responsible Owner the business is ready to change
- DManage transition from old to new ways of working