What role initiates assurance reviews of supplier performance and ensures that lessons learned are implemented?

The correct answer is B. Programme Manager. See the full explanation below for the reasoning.

Question

What role initiates assurance reviews of supplier performance and ensures that lessons learned are implemented?

Options

  • ASenior Responsible Owner
  • BProgramme Manager
  • CBusiness Change Manager
  • DProgramme Office

How the community answered

(42 responses)
  • A
    5% (2)
  • B
    83% (35)
  • C
    2% (1)
  • D
    10% (4)