The correct answer is A. Ensure that the Programme Board assess and understand what the Blueprint means. See the full explanation below for the reasoning.
Question
Which is NOT an area of focus for the Programme Manager when involved in the development of the Blueprint?
Options
- AEnsure that the Programme Board assess and understand what the Blueprint means
- BWork with the Business Change Team to design a coherent Blueprint
- CConfirm the impact on the Blueprint if programme changes are proposed
- DEnsure all outstanding uncertainties in the Blueprint are recorded as risks