Question

Which is NOT an area of focus for the Programme Manager when involved in the development of the Blueprint?

Options

  • AEnsure that the Programme Board assess and understand what the Blueprint means
  • BWork with the Business Change Team to design a coherent Blueprint
  • CConfirm the impact on the Blueprint if programme changes are proposed
  • DEnsure all outstanding uncertainties in the Blueprint are recorded as risks