ECBA · Question #42
When should prioritization of requirements take place?
The correct answer is C. Continually throughout the initiative. Prioritization of requirements is an ongoing activity that must happen continually throughout an initiative because business needs, stakeholder priorities, and constraints evolve over time - a requirement critical at project start may become obsolete, and new high-priority…
Question
When should prioritization of requirements take place?
Options
- AAt the very beginning of an initiative only
- BAfter the maintain requirements and trace requirements tasks have been completed
- CContinually throughout the initiative
- DAfter the maintain requirements task has been completed
How the community answered
(32 responses)- A3% (1)
- B3% (1)
- C94% (30)
Explanation
Prioritization of requirements is an ongoing activity that must happen continually throughout an initiative because business needs, stakeholder priorities, and constraints evolve over time - a requirement critical at project start may become obsolete, and new high-priority requirements can emerge at any stage.
Why the distractors are wrong:
- A is wrong because doing it only at the beginning ignores changes in scope, resources, or business conditions that inevitably occur.
- B is wrong because prioritization is not gated behind other tasks - it operates in parallel with and independent of tracing/maintaining activities, and waiting would delay critical decisions.
- D is wrong for the same reason as B; tying prioritization to the completion of any single task creates an artificial dependency that doesn't reflect real practice.
Memory tip: Think of prioritization like a GPS - it doesn't just set your route once at the start; it recalculates continuously as conditions change. "Continually" = correct.
Topics