ECBA · Question #156

In addition to schedule, which other factor must be considered when evaluating changes to requirements?

The correct answer is A. Number of customers and end-users affected. When considering changes or additions to existing requirements, business analysts assess the impact of the proposed change by considering: Impact: the number of customers or business processes affected if the change is accepted.

Requirements Life Cycle Management

Question

In addition to schedule, which other factor must be considered when evaluating changes to requirements?

Options

  • ANumber of customers and end-users affected
  • BCapacity of the requirements management tool
  • CAmount of time needed to create new documents
  • DAgreement by executive board members

How the community answered

(20 responses)
  • A
    80% (16)
  • B
    10% (2)
  • C
    5% (1)
  • D
    5% (1)

Explanation

When considering changes or additions to existing requirements, business analysts assess the impact of the proposed change by considering: Impact: the number of customers or business processes affected if the change is accepted.

Topics

#change evaluation#stakeholder impact#change factors#requirements change