ECBA · Question #155

When can a change to requirements occur?

The correct answer is B. At any time during the project lifecycle. Proposed Change: can be identified at any time and impact any aspect of business analysis work or deliverables completed to date.

Requirements Life Cycle Management

Question

When can a change to requirements occur?

Options

  • AAs soon as the testing process has begun
  • BAt any time during the project lifecycle
  • COnly after requirements have been approved
  • DOnly after the solution has been designed

How the community answered

(51 responses)
  • A
    2% (1)
  • B
    94% (48)
  • D
    4% (2)

Explanation

Proposed Change: can be identified at any time and impact any aspect of business analysis work or deliverables completed to date.

Topics

#requirements change#project lifecycle#change management#change timing