When can a change to requirements occur?
The correct answer is B. At any time during the project lifecycle. Proposed Change: can be identified at any time and impact any aspect of business analysis work or deliverables completed to date.
Requirements Life Cycle Management
Question
When can a change to requirements occur?
Options
- AAs soon as the testing process has begun
- BAt any time during the project lifecycle
- COnly after requirements have been approved
- DOnly after the solution has been designed
How the community answered
(51 responses)- A2% (1)
- B94% (48)
- D4% (2)
Explanation
Proposed Change: can be identified at any time and impact any aspect of business analysis work or deliverables completed to date.
Topics
#requirements change#project lifecycle#change management#change timing