E_S4HCON2020 · Question #4

You are upgrading a three-system landscape DEV - QAS - PRD. The upgrade project contains a Unicode conversion. You have already upgraded the DEV and the QAS system but not yet the PRD system. What…

The correct answer is D. The upgrade of the PRD must be finished before you import any transports from the upgraded. See the full explanation below for the reasoning.

Question

You are upgrading a three-system landscape DEV - QAS - PRD. The upgrade project contains a Unicode conversion. You have already upgraded the DEV and the QAS system but not yet the PRD system. What do you need to consider? Please choose the correct answer.

Options

  • AThe upgrade of the PRD must be finished before you start new development in the DEV.
  • BThe transport domain of systems DEV and QAS must differ from the transport domain of system
  • CThe transport between Unicode and non-Unicode systems is forbidden.
  • DThe upgrade of the PRD must be finished before you import any transports from the upgraded

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    6% (2)
  • C
    11% (4)
  • D
    77% (27)