You are performing an upgrade with SUM using DMO to an AS ABAP 7.50 based SAP system. You entered a specific number of R3Ioad processes during Roadmap step "Extraction". Where can you change this…
The correct answer is B. In Process Control Center C. In SUM Parameters. See the full explanation below for the reasoning.
Question
You are performing an upgrade with SUM using DMO to an AS ABAP 7.50 based SAP system. You entered a specific number of R3Ioad processes during Roadmap step "Extraction". Where can you change this during the migration via the Utilities option of the SUM UI? There are 2 correct answers to this question Response:
Options
- AIn SUM Phaselist
- BIn Process Control Center
- CIn SUM Parameters
- DIn DMO Migration Preparation
How the community answered
(38 responses)- A18% (7)
- B74% (28)
- D8% (3)