E_S4HCON2020 · Question #31

During an SAP S/4HANA conversion with DMO, which of the following actions take place during the business downtime of the SUM procedure? There are 3 correct answers to this question. Response:

The correct answer is A. Execution of SPAU modification adjustment B. Execution of eCATTs for business validation tests E. Execution of XPRAs and AIMs. See the full explanation below for the reasoning.

Question

During an SAP S/4HANA conversion with DMO, which of the following actions take place during the business downtime of the SUM procedure? There are 3 correct answers to this question. Response:

Options

  • AExecution of SPAU modification adjustment
  • BExecution of eCATTs for business validation tests
  • CCreation of the table structures in the new SAP HANA database
  • DExecution of SPDD modification adjustment
  • EExecution of XPRAs and AIMs

How the community answered

(27 responses)
  • A
    78% (21)
  • C
    7% (2)
  • D
    15% (4)