E_S4CON_2505 · Question #16
During an SAP S/4HANA conversion with DMO, which of the following actions take place during the business downtime of the SUM procedure? There are 3 correct answers to this question.
The correct answer is A. Execution of SPAU modification adjustment B. Execution of eCATTs for business validation tests E. Execution of XPRAs and AIMs. During business downtime in the SUM/DMO procedure, the system is locked to business users, and the remaining import, adjustment, and validation steps are finalized. SPAU (option A) adjusts modified repository objects (programs, function modules) at this stage because they…
Question
During an SAP S/4HANA conversion with DMO, which of the following actions take place during the business downtime of the SUM procedure? There are 3 correct answers to this question.
Options
- AExecution of SPAU modification adjustment
- BExecution of eCATTs for business validation tests
- CCreation of the table structures in the new SAP HANA database
- DExecution of SPDD modification adjustment
- EExecution of XPRAs and AIMs
How the community answered
(41 responses)- A78% (32)
- C15% (6)
- D7% (3)
Explanation
During business downtime in the SUM/DMO procedure, the system is locked to business users, and the remaining import, adjustment, and validation steps are finalized. SPAU (option A) adjusts modified repository objects (programs, function modules) at this stage because they depend on the completed software import. XPRAs and AIMs (option E) are post-import routines that activate and initialize new functionality - they run automatically after the import finishes, squarely within the downtime window. eCATTs (option B) are used as automated regression/validation tests to confirm business processes are intact before the system is handed back to users, making them a downtime activity.
Option C is wrong because table structure creation in the new SAP HANA database happens before business downtime, during the shadow system/preparation phase - this is a key DMO advantage that reduces actual downtime. Option D is wrong because SPDD (Data Dictionary object adjustments for tables, structures, domains) must be completed before downtime so the dictionary is consistent prior to data migration.
Memory tip: Think "SPDD before, SPAU after the lock" - alphabetically D comes before A, just as SPDD happens before downtime and SPAU happens after the downtime lock begins. Table creation (C) also happens before, while XPRAs/AIMs and eCATTs close out the downtime phase.