E_S4CON_2505 · Question #15

Which step can be optimized when you provide the MIGRATE_DT_DUR.XML file to SUM?

The correct answer is B. Downtime migration. Providing MIGRATE_DT_DUR.XML to SUM (Software Update Manager) gives it pre-measured duration data from a prior migration run, allowing it to optimize the Downtime Migration step (B) by skipping the re-estimation phase and using the cached timings directly - reducing overall…

Database Migration Option (DMO) of SUM

Question

Which step can be optimized when you provide the MIGRATE_DT_DUR.XML file to SUM?

Options

  • ADowntime conversion
  • BDowntime migration
  • CShadow on target creation
  • DSilent data migration (SDM)

How the community answered

(23 responses)
  • A
    9% (2)
  • B
    74% (17)
  • C
    4% (1)
  • D
    13% (3)

Explanation

Providing MIGRATE_DT_DUR.XML to SUM (Software Update Manager) gives it pre-measured duration data from a prior migration run, allowing it to optimize the Downtime Migration step (B) by skipping the re-estimation phase and using the cached timings directly - reducing overall downtime.

Why the distractors are wrong:

  • A (Downtime Conversion) involves data type/format conversion during downtime, which is a separate process not influenced by this duration file.
  • C (Shadow on Target Creation) is an uptime phase where the shadow system is built; duration data from a prior migration run has no role in creating it.
  • D (Silent Data Migration) runs in the background during uptime and operates independently of downtime duration estimates.

Memory tip: Decode the filename - MIGRATE_DT_DUR.XML = Migrate + DownTime + Duration. The name literally spells out what it optimizes: the downtime migration duration.

Topics

#MIGRATE_DT_DUR.XML#downtime migration#DMO optimization