Question

A customer is running Exchange 2010 on an EMC VNX. The customer recovery SLA mandates they cannot lose more than 10 MB of mail data, and the mail system cannot be down for more than five minutes. What should you implement to meet these recovery objectives without impacting Exchange performance or the recovery SLA?

Options

  • AUse a DAG with three database copies
  • BUse Replication Manager with Clones
  • CUse Replication Manager with snapshots
  • DUse log shipping with MirrorView/A