While running the Backend Cabling Verification script, the LEDs do not match the SymmWin graphic. It halts with a message that there is a cabling error and advises moving cables. Which service…
The correct answer is A. Data center move. See the full explanation below for the reasoning.
Question
While running the Backend Cabling Verification script, the LEDs do not match the SymmWin graphic. It halts with a message that there is a cabling error and advises moving cables. Which service engagement would require PSE intervention prior to moving the cables?
Options
- AData center move
- BInstallation
- CDAE addition
- DStorage bay addition
How the community answered
(38 responses)- A82% (31)
- B3% (1)
- C11% (4)
- D5% (2)