When using a 10 TB single X-Brick, what is the minimum amount of data that should be written during the Fill phase of the PoC Toolkit?
The correct answer is C. 20 TB. Per IDC's best practices the toolkit fills the array 2x.
Perform CLARiiON System Maintenance
Question
When using a 10 TB single X-Brick, what is the minimum amount of data that should be written during the Fill phase of the PoC Toolkit?
Options
- A10 TB
- B15 TB
- C20 TB
- D30 TB
How the community answered
(64 responses)- A6% (4)
- B11% (7)
- C80% (51)
- D3% (2)
Explanation
Per IDC's best practices the toolkit fills the array 2x.
Topics
#PoC Toolkit#Fill phase#XtremIO testing#capacity planning