Question
After acquiring a company 300 hundred miles from their current office, a customer has asked EMC to help to design a single-hop application recovery plan. After careful analysis of the workload and available bandwidth, SRDF/AR was selected as the solution. If the SRDF/AR cycle time is set to 90 minutes, what is the maximum potential data loss?
Options
- A1.5 hours of data
- B2 hours of data
- C3 hours of data
- D4.5 hours of data