Two SRDF/A sessions are grouped together to be managed using Multi-Session Consistency. What happens to cycle switching if Session 1 completes its current Transmit cycle before Session 2 can…
The correct answer is A. Cycle switch for both sessions will be delayed. See the full explanation below for the reasoning.
Question
Two SRDF/A sessions are grouped together to be managed using Multi-Session Consistency. What happens to cycle switching if Session 1 completes its current Transmit cycle before Session 2 can complete its current Transmit cycle?
Options
- ACycle switch for both sessions will be delayed
- BBoth sessions will be dropped
- CCycle switch for Session 1 will proceed independently of Session 2
- DCycle switching will be suspended for both sessions
How the community answered
(62 responses)- A74% (46)
- B6% (4)
- C5% (3)
- D15% (9)
Community Discussion