The correct answer is C. 2 hours of data. See the full explanation below for the reasoning.

Question

After acquiring a company 300 hundred miles from their current office, a customer has asked EMC to help design a single-hop application recovery plan. After careful analysis of the workload and available bandwidth, SRDF/AR was selected as the solution. If the SRDF/AR cycle time is set to 60 minutes, what is the maximum potential data loss?

Options

  • A1 hours of data
  • B1.5 hours of data
  • C2 hours of data
  • D3 hours of data