E20-326 · Question #117
You are designing a new disaster recovery solution with VMAX arrays. During the initial project kick- off meeting, the customer reports the maximum allowable downtime for their applications is…
The correct answer is A. Defer making a recommendation until the application RPO in known. See the full explanation below for the reasoning.
Question
You are designing a new disaster recovery solution with VMAX arrays. During the initial project kick- off meeting, the customer reports the maximum allowable downtime for their applications is ninety minutes, but they have not yet determined how much data recovery following a disaster their environment can tolerate. The customer asks which remote replication method you recommend for their environment. What do you recommend?
Options
- ADefer making a recommendation until the application RPO in known.
- BRecommend the disaster recovery solution as described in the Sales Order.
- CDefer making a recommendation until the application RTO is known.
- DRecommend the disaster recovery solution described in the Statement of Work.
How the community answered
(70 responses)- A76% (53)
- B13% (9)
- C7% (5)
- D4% (3)