Question
You are designing a new disaster recovery solution with VMAX arrays. During the initial project kick- off meeting, the customer reports their environment can tolerate five minutes or less of data recovery following a disaster but have not yet determined the maximum allowable downtime for their applications. The customer asks which remote replication methods you recommend for their environment. What do you recommend?
Options
- ADefer making a recommendation until the application RTO is known.
- BRecommend the disaster recovery solution as described in the Sales Order.
- CDefer making a recommendation until the application RPO in known.
- DRecommend the disaster recovery solution described in the Statement of Work.