nerdexam
Dell-EMC

E20-326 · Question #116

E20-326 Question #116: Real Exam Question with Answer & Explanation

The correct answer is A. Defer making a recommendation until the application RTO is known.. See the full explanation below for the reasoning.

Question

You are designing a new disaster recovery solution with VMAX arrays. During the initial project kick- off meeting, the customer reports their environment can tolerate five minutes or less of data recovery following a disaster but have not yet determined the maximum allowable downtime for their applications. The customer asks which remote replication methods you recommend for their environment. What do you recommend?

Options

  • ADefer making a recommendation until the application RTO is known.
  • BRecommend the disaster recovery solution as described in the Sales Order.
  • CDefer making a recommendation until the application RPO in known.
  • DRecommend the disaster recovery solution described in the Statement of Work.

Community Discussion

No community discussion yet for this question.

Full E20-326 Practice