You are designing a new disaster recovery solution with VMAX arrays. During the initial project kick- off meeting, the customer reports their environment can tolerate five minutes or less of data…

The correct answer is A. Defer making a recommendation until the application RTO is known. See the full explanation below for the reasoning.

Question

You are designing a new disaster recovery solution with VMAX arrays. During the initial project kick- off meeting, the customer reports their environment can tolerate five minutes or less of data recovery following a disaster but have not yet determined the maximum allowable downtime for their applications. The customer asks which remote replication methods you recommend for their environment. What do you recommend?

Options

  • ADefer making a recommendation until the application RTO is known.
  • BRecommend the disaster recovery solution as described in the Sales Order.
  • CDefer making a recommendation until the application RPO in known.
  • DRecommend the disaster recovery solution described in the Statement of Work.

How the community answered

(18 responses)
  • A
    78% (14)
  • B
    6% (1)
  • C
    6% (1)
  • D
    11% (2)