Dell-EMC
E20-260 · Question #48
VPLEX ndu pre-check command reports a time drift between directors and the Management Server. How must the NDU be performed?
The correct answer is A. The NDU cannot be started.the time drift must be resolved. See the full explanation below for the reasoning.
Question
VPLEX ndu pre-check command reports a time drift between directors and the Management Server. How must the NDU be performed?
Options
- AThe NDU cannot be started.the time drift must be resolved.
- BThe NDU can be started using --skip-confirmations option.
- CThe NDU can be started.the time drift will be automatically fixed during upgrade.
- DThe NDU must be started using the --force option.
How the community answered
(47 responses)- A72% (34)
- B9% (4)
- C4% (2)
- D15% (7)
Community Discussion
No community discussion yet for this question.