Dell-EMC
E20-260 · Question #47
How do you verify that the VPLEX upgrade has completed successfully?
The correct answer is D. Run the ndu pre-check command. See the full explanation below for the reasoning.
Question
How do you verify that the VPLEX upgrade has completed successfully?
Options
- ALog into the VPLEX Unisphere interface.
- BRun the cluster-summary command.
- CCheck that the system LED is green on each director.
- DRun the ndu pre-check command.
How the community answered
(35 responses)- A6% (2)
- B3% (1)
- C11% (4)
- D80% (28)
Community Discussion
No community discussion yet for this question.