E20-027 · Question #62
As represented in the exhibit, a company has a system with three critical components. Each component must be functioning for the system to be operational. SLAs have been established between the…
The correct answer is B. 81.7. See the full explanation below for the reasoning.
Question
As represented in the exhibit, a company has a system with three critical components. Each component must be functioning for the system to be operational. SLAs have been established between the business and IT that define normal hours of operations for service as 8 A.M. - 8 P.M., Monday through Friday. What is the availability (percentage) of Component 1?
Exhibit
Options
- A78
- B81.7
- C89
- D91.7
How the community answered
(47 responses)- A9% (4)
- B85% (40)
- C2% (1)
- D4% (2)
Community Discussion
No community discussion yet for this question.