The exhibit represents a Component Failure Impact Analysis (CFIA) for a company's IT infrastructure. Several Requests for Change (RFC) were raised. Which RFC should be considered a priority for…
The correct answer is A. Deploying a switch architecture with no single point of failure. See the full explanation below for the reasoning.
Question
The exhibit represents a Component Failure Impact Analysis (CFIA) for a company's IT infrastructure. Several Requests for Change (RFC) were raised. Which RFC should be considered a priority for implementation?
Exhibit
Options
- ADeploying a switch architecture with no single point of failure
- BClustering the backup server with multiple storage devices
- CConfiguring the NAS device in an active-active mode
- DAdding more disk drives to the storage array
How the community answered
(57 responses)- A82% (47)
- B5% (3)
- C11% (6)
- D2% (1)