E20-007 · Question #61

What is a core deliverable at the end of the analytic project?

The correct answer is C. A presentation for project sponsors. See the full explanation below for the reasoning.

Question

What is a core deliverable at the end of the analytic project?

Options

  • AAn implemented database design
  • BA whitepaper describing the project and the implementation
  • CA presentation for project sponsors
  • DThe training materials

How the community answered

(30 responses)
  • A
    17% (5)
  • B
    10% (3)
  • C
    70% (21)
  • D
    3% (1)