What is an accurate statement if the recovery time objective (RTO) of an application is 4 hours?
The correct answer is B. Production must be resumed within 4 hours after a failure. BC Terminologies Recovery-Point Objective (RPO): This is the point-in-time to which systems and data must be recovered after an outage. It defines the amount of data loss that a business can endure. Based on the RPO, organizations plan for the frequency with which a backup or…
Question
What is an accurate statement if the recovery time objective (RTO) of an application is 4 hours?
Exhibit
Options
- ANo more than 4 hours of production data can be lost
- BProduction must be resumed within 4 hours after a failure
- CMean time to repair the application is at least 4 hours
- DMean time between application failure is 4 hours
How the community answered
(21 responses)- A5% (1)
- B76% (16)
- C14% (3)
- D5% (1)
Explanation
BC Terminologies Recovery-Point Objective (RPO): This is the point-in-time to which systems and data must be recovered after an outage. It defines the amount of data loss that a business can endure. Based on the RPO, organizations plan for the frequency with which a backup or replica must be made. An organization can plan for an appropriate BC technology solution on the basis of the Recovery-Time Objective (RTO): The time within which systems and applications must be recovered after an outage. It defines the amount of downtime that a business can endure and