Question
What is the problem with oversizing the UPS system within a data center?
Options
- AIt limits the growth capacity of the data center.
- BIt decreases the mean time to recover (MTTR).
- CIt increases the number of single points of failure.
- DIt drives excessive capital and maintenance expenses.