The correct answer is D: Workbooks. Power BI deployment pipelines support datasets, reports, and dashboards across stages, but Workbooks (Excel workbooks published to Power BI) cannot be included.

Implement and manage a data analytics environment

Question

Assume that you are responsible for designing a deployment pipeline for your project's Power BI assets. As part of the deployment strategy which item from the following list CAN NOT be copied as part of the deployment pipeline?

Options

  • ADatasets
  • BReports
  • CData charts
  • DWorkbooks

Explanation

Power BI deployment pipelines support datasets, reports, and dashboards across stages, but Workbooks (Excel workbooks published to Power BI) cannot be included.

Common mistakes.

  • A. Datasets are fully supported deployment pipeline items and can be copied and promoted between pipeline stages.
  • B. Reports are fully supported deployment pipeline items and can be promoted between stages along with their associated datasets.
  • C. 'Data charts' is not a recognized Power BI item type; this is a distractor. Dashboards, which are a real Power BI item type, are supported by deployment pipelines.

Concept tested. Power BI deployment pipeline supported and unsupported item types

Reference. https://learn.microsoft.com/en-us/power-bi/create-reports/deployment-pipelines-overview

Topics

#Power BI Deployment Pipelines#Power BI Assets#Deployment Strategy#Power BI Service

Community Discussion

No community discussion yet for this question.

Full DP-500 PracticeBrowse All DP-500 Questions