You have an Azure Data Factory pipeline named P1. You need to schedule P1 to run at 10:15 AM, 12:15 PM, 2:15 PM, and 4:15 PM every day. Which frequency and interval should you configure for the…
The correct answer is B. Frequency: Day. The frequency is a Day and interval 1, since every day should execute 4x. Within a day 4 times
Submitted by fatema_kw· Mar 30, 2026Develop data processing
Question
You have an Azure Data Factory pipeline named P1. You need to schedule P1 to run at 10:15 AM, 12:15 PM, 2:15 PM, and 4:15 PM every day. Which frequency and interval should you configure for the scheduled trigger?
Options
- AFrequency: Month
- BFrequency: Day
- CFrequency: Minute
- DFrequency: Hour
How the community answered
(61 responses)- A18% (11)
- B72% (44)
- C7% (4)
- D3% (2)
Explanation
The frequency is a Day and interval 1, since every day should execute 4x. Within a day 4 times