DATABRICKS-CERTIFIED-PROFESSIONAL-DATA-SCIENTIST · Question #56
You are working on a Data Science project and during the project you have been gibe a responsibility to interview all the stakeholders in the project. In which phase of the project you are?
The correct answer is A. Discovery. During the discovery phase you will be interviewing all the project stakeholders because they would be having quite a good amount of knowledge for the problem domain you will be working and you also interviewing project sponsors you will get to know what all are the…
Question
You are working on a Data Science project and during the project you have been gibe a responsibility to interview all the stakeholders in the project. In which phase of the project you are?
Options
- ADiscovery
- BData Preparations
- CCreating Models
- DExecuting Models
- ECreating visuals from the outcome
- FOperationnalise the models
How the community answered
(65 responses)- A85% (55)
- C3% (2)
- D2% (1)
- E8% (5)
- F3% (2)
Explanation
During the discovery phase you will be interviewing all the project stakeholders because they would be having quite a good amount of knowledge for the problem domain you will be working and you also interviewing project sponsors you will get to know what all are the expectations once project get completed. Hence, you will be noting down all the expectations from the project as well as you will be using their expertise in the domain.