Which two additional Q-in-Q VLAN tunnel configuration steps must be followed if the provider network uses a VXLAN overlay?
The correct answer is A. Configure VLAN Translation. B. Map the SVLAN traffic to a VNI. Configure VLAN Translation (A): VLAN translation is necessary to translate customer VLANs (CVLANs) to service VLANs (SVLANs) for Q-in-Q tunneling in a VXLAN environment. Map the SVLAN traffic to a VNI (B): SVLAN traffic must be mapped to a VXLAN Network Identifier (VNI) for…
Question
Which two additional Q-in-Q VLAN tunnel configuration steps must be followed if the provider network uses a VXLAN overlay?
Options
- AConfigure VLAN Translation.
- BMap the SVLAN traffic to a VNI.
- CRemove the CVLAN-to-SVLAN mapping.
- DConfigure the BGP route-target and route-distinguisher.
How the community answered
(23 responses)- A70% (16)
- C9% (2)
- D22% (5)
Explanation
Configure VLAN Translation (A): VLAN translation is necessary to translate customer VLANs (CVLANs) to service VLANs (SVLANs) for Q-in-Q tunneling in a VXLAN environment. Map the SVLAN traffic to a VNI (B): SVLAN traffic must be mapped to a VXLAN Network Identifier (VNI) for encapsulation and transport across the VXLAN overlay network.