D-PST-DY-23 · Question #41
What are three requirements of asynchronous file replication? (Choose three.)
The correct answer is C. Create bond 1 and Tag replication. D. Create Remote System. E. Configure File Mobility Network. Asynchronous file replication on Dell PowerStore requires three key setup steps: Create bond 1 and Tag replication (C) establishes the dedicated network bond and VLAN tagging needed to carry replication traffic; Create Remote System (D) defines the target PowerStore array so…
Question
Options
- ACreate FC zoning between PowerStore.
- BConfigure Data Storage Network.
- CCreate bond 1 and Tag replication.
- DCreate Remote System.
- EConfigure File Mobility Network.
How the community answered
(59 responses)- A5% (3)
- B15% (9)
- C80% (47)
Explanation
Asynchronous file replication on Dell PowerStore requires three key setup steps: Create bond 1 and Tag replication (C) establishes the dedicated network bond and VLAN tagging needed to carry replication traffic; Create Remote System (D) defines the target PowerStore array so the source knows where to send replicated data; and Configure File Mobility Network (E) sets up the network path specifically used to move file data between systems during replication.
Why A is wrong: FC (Fibre Channel) zoning is a block-storage SAN concept - file replication uses IP-based networking, not FC fabric. Why B is wrong: "Data Storage Network" is not a recognized configuration step in the PowerStore file replication workflow; it conflates generic storage networking terminology with a specific replication requirement.
Memory tip: Think "Bond, Remote, Mobility" - you Bond the network, name the Remote target, and enable file Mobility. In that order, you've built the highway, identified the destination, and loaded the truck.