D-MSS-DS-23 · Question #24

A technical architect is helping a customer prepare for a data center maintenance window. All applications must failover to the disaster recovery site. The customer also wants to test their disaster…

The correct answer is B. Planned failover from source site. For a customer preparing for a data center maintenance window and wanting to test their disaster recovery plan, the recommended PowerStore Manager replication option is a planned failover from the source site. This process involves initiating the failover from the source site…

Data Protection and Availability Design

Question

A technical architect is helping a customer prepare for a data center maintenance window. All applications must failover to the disaster recovery site. The customer also wants to test their disaster recovery plan. What PowerStore Manager replication option should be used to address the customer's need, and from which site should the option be run?

Options

  • APlanned failover from target site
  • BPlanned failover from source site
  • CFailover from source site
  • DFailover from target site

How the community answered

(40 responses)
  • A
    8% (3)
  • B
    78% (31)
  • C
    3% (1)
  • D
    13% (5)

Explanation

For a customer preparing for a data center maintenance window and wanting to test their disaster recovery plan, the recommended PowerStore Manager replication option is a planned failover from the source site. This process involves initiating the failover from the source site, ensuring a controlled transition of applications and services to the disaster recovery site. Planned failover allows for testing the disaster recovery plan while maintaining data integrity.

Topics

#PowerStore replication#planned failover#disaster recovery#DR testing