Dell-EMC
D-ISM-FN-23 · Question #71
A system has three components and all three components need to be operational for 24 hours; Monday through Friday. During a particular week, failure of component 3 occurred as follows: -Tuesday = 8…
The correct answer is B. 35 hours. See the full explanation below for the reasoning.
Question
A system has three components and all three components need to be operational for 24 hours; Monday through Friday. During a particular week, failure of component 3 occurred as follows:
-Tuesday = 8 AM to 1 PM -Thursday = 5 PM to 10 PM -Friday = 5 AM to 10 AM What is the mean time between failures on component 3 for that week?
Options
- A5 hours
- B35 hours
- C40 hours
- D51 hours
How the community answered
(20 responses)- A5% (1)
- B85% (17)
- D10% (2)
Community Discussion
No community discussion yet for this question.